单选题During initial cluster planning session, a requirement is mandated that application monitoring will  Be used to monitor the production database and three application servers. Since all the application servers rely on the database being active, only one

题目内容(请给出正确答案)
单选题
During initial cluster planning session, a requirement is mandated that application monitoring will  Be used to monitor the production database and three application servers. Since all the application servers rely on the database being active, only one resource group has been planned to manage the starting/stopping of the cluster resources.  How ill the initial design impact the use of application monitoring?()
A

 Only one application server per resource group can be monitored.

B

 Process monitoring is part of RSCT and requires no special scripts.

C

 Any application can be monitored as long as it has an application server.

D

 Having all application servers in one resource group improves recovery time.

参考答案和解析
正确答案: A
解析: 暂无解析